We have spent the last weekend extending the front fence to the south of the house along the road frontage, replacing the old wooden post and rail fence that was originally there a hundred and thirty years ago. We know that there was a post and rail fence, because the massive corner post on the northern boundary, with its 3 mortices in it, was still standing there in 1976 when we came here. I would have kept it there, as i saw it as a bit of heritage, but when the land next door was bought by the new neighbours, they dug it out one day without telling us and replaced it with piece of rusty steel pipe that was obtained from the local coal mine.
We spent the first day of the weekend digging the 17 post holes down to 600mm depth. I borrowed a ‘kanga’ machine with a post hole auger the make the job easier, but it still took all day, as we kept hitting big rocks and huge tree roots, so many of the holes had to be done by hand with a crow bar and fencing shovel.

Something quite amazing happened in the 2nd last hole. This is 100 metres from the site of the old wooden corner post. I lined up the position of the fence using a long builders tape and a string line. I really just relied on lining it up visually with the string line, however, I was pretty confident that it was more or less in the correct place. If anything, I was tending to err on the side of caution. maybe 100mm in from the border line?
When I tried the bore the 2nd last hole, I hit what appeared to be a tree root, but it was quite vertical. I had to dig it out by hand with the bar and shovel. When I got down to the 600 mm level that I needed, I found that the ‘root’ was a slightly loose, so I managed to pull it up and out. it was only then that I realised that I had found one of the original wooden posts, dating back 127 years. It had rotted off at ground level and down 300 mm below ground level, but was preserved intact between 600mm and 800mm deep in the airless conditions deep down.


What are the odds of keeping the fence line perfectly straight with the old non-existent fence, working down 100 metres from the original corner post. BUT, then to dig a fence post hole directly on top of the original one! I was amazed, staggered actually.


You can see in this image that although the forest around us is still burnt black, some of the trunks off the older eucalypts are starting to re-shoot from epicormic buds on the main trunk of the trees.
Janine mixed the cement and dry sand mix for me to ram into the fence post holes, so as to set the post straight. I did all the ramming and levelling. We even made our own hand made rubble from crushed building waste from the burnt out old pottery building.



After ramming in and concreting the 17 fence posts on the 2nd day with the ramming bar, my hands, wrists, elbows and shoulders were quite strained and sore. I needed to have 2 days off to recover! I’m not used to such heavy and punishing work like this on my body at this older age.
During the week, we lifted, scraped and cleaned 1000 old recycled roofing slates that we had stored along the fence line of the old stone fruit orchard. We are intending to build the new pottery on the stone fruit orchard site, so everything has t one shifted and cleaned up. we moved the slates to a new storage place under the verandah of the old Railway Station. We always intended to use these old roof slates as floor tiles in the old pottery, but as we didn’t have any concrete floors, just pavers set in sand, it was not possible to use them at that time. They will find a place in the new pottery.



That was two days of bending and and scraping, different from post hole ramming, but it still feels like work, just not as brutal on the joints.
Our next job this week was to dig up all the stone retaining wall along the old pottery site and stack the stones off sit, ready for re-use as a new stone retaining wall for the new pottery, once the site is cleared. We will need to raise the level at the back of the site about 500 to 600 mm high to get a reasonable level.


We need to find sufficient stones to build a wall 600 mm high and 25 metres long. We will be scrounging every stone on the block to get there.
Our last job today was to level out the 5 tonnes of rock dust that we had delivered to make a base for our new water tank. It needs to be 4.5 metres in diameter, solid, well compacted and reasonably level. We have had a couple of goes at it, over the week, in between bouts of rain, which was very good at settling it down and compacting it. This afternoon we got it just about right. One more shower of rain will do it good.

You must be logged in to post a comment.